Store planning
Shop Fit-Out Checklist: Six Weeks to Opening Day in Thailand
Work backwards from opening day: landlord rules and a fixture schedule first, made-to-order next, standard pieces after approval. Six weeks is a planning band, not a promise.
A shop fit-out checklist for six weeks to opening day in Thailand is a calendar, not a moodboard. Independent retailers lose the opening date when they buy a beautiful counter first and only later discover the mall will not allow wall fixings, the cash wrap cannot hide a printer, or the slatwall arrives without hangrails. The useful sequence is the reverse of what most owners do: lock the building rules, write a fixture schedule, quote the package, then install — with made-to-order pieces specified early enough that standard racks and mannequins are not waiting on a drawing.
Six weeks is a planning band for a first or second independent shop of roughly 20–80 square metres, not a promise that every project fits it. A fully custom joinery room, a landlord who answers slowly, or a unit you have not measured yet needs more calendar. A pop-up with only rolling racks needs less. Use the weeks below as a fixture-first order of work.
What this checklist is for — and what it is not
This checklist is for owners who already have a unit, or who will have keys shortly, and who need walls, rails, a cash wrap, and opening-day merchandising to land together. It is written around shopfitting and retail display, not around civil work.
It is not:
- A construction programme for demolition, MEP, or a full interior design package.
- A price. Delivery into a mall, evening labour windows, and finish choices move totals more than one extra faceout.
- A lead-time guarantee. Fabrication and freight belong on a written quotation against your drawings and address, not in a blog.
If you do not yet have a fixture list, start with the retail store fixtures buyer’s guide and, for clothing, what a 40 sqm boutique needs. This page puts those lists on a clock.
The six-week view
| Week | Owner job | Fixture job | Decision that must be closed |
|---|---|---|---|
| 6 | Measure the selling floor; collect landlord rules | Draft the fixture schedule by zone | Wall-mounted vs freestanding; cash-wrap location |
| 5 | Send shop type, size, photos, opening month | Split standard vs made-to-order; request one quotation | Finish direction; language of the quote |
| 4 | Approve the written quote or send a marked-up list | Lock custom drawings for counters and awkward walls | Who receives on site; installation included or not |
| 3 | Confirm access: lifts, loading dock, night work | Standard fixtures can be ordered against the approved list | Accessory counts (hooks, hangrails, shelves) |
| 2 | Clear the unit; mark drill points or unit positions | Made-to-order should be in production; standard in motion | Fitting-room hardware and signage on the same list |
| 1 | Staff walkthrough of cash wrap and stockroom | Install, level, load accessories, merchandising reset | Punch list: missing hooks, door swings, packing space |
Work backwards from opening day. If today is already inside week 3, cut custom joinery, not the cash wrap.
Week 6 — Measure the shop, not the lease
Lease area is not selling floor. Subtract fitting rooms, a back room, staff toilet, and any landlord corridor. Fixture counts belong to what customers walk.
On site, mark four things before anyone prices a panel:
- Door swing and the first two metres. That zone is for orientation, not a four-way rack.
- The two longest walls and whether you may drill them. Mall versus street often decides this before taste does.
- Cash wrap position that does not block the door, fitting rooms, or a fire route. Plan it as a workflow, not a timber finish.
- Power and data for terminals, lighting, and any lightbox — even if signage is a separate workshop.
Photograph empty walls, columns, and the goods-lift door. A manufacturer who has to guess millimetres will pad the quote or get the run wrong.
Write the shop type in one paragraph: fashion, beauty, gift, mixed. Slatwall vs gridwall vs pegboard is a week-6 decision if the walls will carry the assortment. Do not leave the wall system until week 2.
Week 5 — One fixture schedule, one quotation
Turn the photos into a schedule: product, size, quantity, finish, zone. Every slatwall wall needs hangrails, faceouts, and shelves as line items, not as “hooks later.” Empty grooves on opening day are cheaper than a second courier run of the wrong accessory.
Split the list:
- Standard — many slatwall panels, gridwall, rolling racks, mannequins, a large share of hooks and acrylic. These can move once the list is approved.
- Made-to-order — cash wraps, branded reception, odd showcase sizes, anything that absorbs a column. These need drawings and sit on the critical path.
Ask for one written quotation, Thai or English, that states delivery to site, who unloads, and whether installation is included. Four factory WhatsApp prices are not comparable. Store fixtures vs custom packages is the decision you are making this week, not a personality upgrade.
Foreign owners should insist the same schedule exists in English, with delivery and installation as explicit lines. The process is in buying shop fixtures in Thailand as a foreign owner; week 5 is when that document has to exist.
Week 4 — Approve, then stop redesigning the wall
A quotation that is “almost right” is still not a production instruction. Mark the list: delete the extra four-way, add fitting-room hooks, confirm the cash wrap has bag storage and a printer void. Send one marked-up schedule, not a new moodboard.
This is the last comfortable week to change made-to-order dimensions. Changing a cash wrap width after drawings are issued is how opening week eats the packing counter. Standard rails can still move; the counter should not.
Confirm in writing:
- Site address and access notes (mall loading hours, no lift, walk-up).
- Who is present to receive.
- Installation included or excluded.
- Finish samples if the visible timber or metal must match across wall, rail, and wrap.
If the landlord still has not answered on drilling, assume freestanding until you have paper. Hoping for a verbal “it should be fine” is how week 1 becomes a floor of rails you did not want.
Week 3 — Access, accessories, and the items that still get forgotten
By week 3 the list should be stable. The work is logistics and the unglamorous line items that make a wall usable.
Count accessories against the SKU list, not against empty grooves. A fashion wall without enough hangrail is panelling. A beauty wall without tester space is a carton dump. Fitting rooms need hooks, a seat or ledge, and a door or curtain that closes — they are fixtures, and they belong on the same quote.
Signage belongs on the schedule even when a different workshop makes it. A lightbox that arrives after slatwall is fitted will fight the wall you already paid to finish.
If you sell hanging garments, decide now whether floor capacity is one rail or two. Clothing racks vs slatwall is the split: walls hold depth, rails hold the story. Adding a third rail in week 1 because the room “feels empty” is how 40 square metres stops walking.
Week 2 — Clear the unit and freeze the walk
The selling floor should be empty enough to mark positions. Tape the cash wrap footprint, the door swing, and the first aisle. Walk it with a colleague carrying two shopping bags. If you cannot pass, the fixture is in the wrong place — not “we will see on install day.”
Made-to-order pieces should already be in production. This is not the week to invent a new reception desk. It is the week to confirm the install sequence: walls and wrap first, then floor fixtures, then mannequins and countertop displays. Loading a table before the wall is up is how merchandise gets dirty and how installers trip.
Back-room storage is part of opening. Overflow on the selling floor is not a merchandising concept. One stock rail or shelf in the back is cheaper than a seventh floor fixture.
Week 1 — Install, punch, merchandise
Installation week is a punch list, not a design studio.
- Confirm the crew can enter: loading dock booking, lift padding, night window if the mall requires it.
- Walls and cash wrap land first. Level, fix, and only then hang accessories.
- Load hangrails, faceouts, shelves, and hooks to the quantities on the quote — not “fill every groove.”
- Place floor rails and the feature table with the walk still clear to the wrap and fitting rooms.
- Mannequins last, where the outfit is visible from the door without blocking it.
- Walk the cash wrap as a staff member: bag, terminal, printer, returns pile. If packing failed, the wrap was specified as furniture.
Do not add fixtures because the room looks sparse on day two. A 40 sqm boutique should look slightly quiet in week one of trading. Depth belongs on the wall; the floor is for walking and one story.
When six weeks is the wrong band
Shorten the calendar when the package is almost all standard rolling racks and gridwall for a temporary booth. Lengthen it when:
- The cash wrap or full wall joinery is custom and drawings are not started.
- The mall has not issued fit-out rules.
- You have not measured the unit.
- Beauty or jewellery needs tester runs and enclosed cases as well as open walls — see the cosmetics fixture checklist rather than forcing a fashion calendar onto a different shop.
A late start is not fixed by ordering more pieces. It is fixed by cutting custom work and protecting the cash wrap, the wall system, and fitting rooms.
Common mistakes on a six-week clock
- Moodboard before millimetres. Photographs of foreign flagships do not survive a Thai mall’s no-drill rule.
- Four quotes, four scopes. Compare one schedule, not four WhatsApp numbers.
- Accessories as an afterthought. They are the wall.
- Cash wrap chosen by finish. Staff cannot pack on a sculpture.
- Signage left off the fixture list. It arrives last and fights the perimeter.
- Inventing a new counter in week 2. That is how opening day has no bag storage.
- Asking for a price before a list. You will get four incomparable figures and no install date you can plan around.
What to send this week
You do not need a professional interior set. You need enough to stop guessing:
- Shop type and what you sell.
- City, mall or street, and approximate selling-floor size.
- Opening month.
- Photos or a sketch of the empty unit.
- Any landlord constraint already in writing.
- Language you want the quotation in.
That is a week-6 / week-5 package. Retail Supply Thai will turn it into a fixture schedule and one written quotation — Thai or English — instead of four factory threads that do not share a calendar.
Get the six weeks onto one plan
If your opening date is inside two months, start with the schedule, not with a single product photograph. Send the shop type, the size, and the month you need to trade. We will put the walls, the wrap, and the floor fixtures on one list so the last week is installation, not invention.
Common questions
- Can I fit out a shop in less than six weeks?
- Yes, if the package is mostly standard fixtures and the unit is already measured with landlord rules in writing. Cut made-to-order joinery first, not the cash wrap or fitting rooms.
- When should I request a quotation?
- In week 5, once you have shop type, selling-floor size, photos, and the opening month. A price before a fixture schedule produces four incomparable numbers.
- What if the mall has not approved wall fixings?
- Plan freestanding walls until you have written permission. Do not order a full-height wall-mounted run on a verbal maybe.
- Does this checklist include construction and electrical work?
- No. It is a fixture and merchandising sequence. Civil work, MEP and a full interior package sit on a separate programme and usually need more calendar than six weeks.